EPA Evaluates Pump Station Size:
The EPA concludes that LADWP’s proposal for a 150 cfs pump station is not
well-supported and that available evidence strongly suggests LA prefers this
alternative in order to build future capacity for additional water exports from
Owens Valley.
The Lower Owens River Project (LORP) is mitigation for impacts caused by
groundwater pumping in the Owens Valley. When initially proposed, many valley
residents were concerned that this could be used as a “third barrel” of the
aqueduct to export even more groundwater. To calm these fears, LADWP “promised”
that it would not be used for this and pointed to the absolute 50 cfs limit to
the pumpback station spelled out in the Longterm Groundwater Management
Agreement. True to form, as soon as the writ was discharged from the Third
District Court, LADWP set about re-interpreting the Longterm Agreement and
Memorandum of Understanding by planning a 150 cfs pumpback station capable of
exporting additional groundwater in excess of the mandated river flows.
As the EPA indicates below, LADWP's planning of a larger pumpback station has
substantially delayed implementation of mitigation and is economically
infeasible unless LA intends to increase groundwater pumping in the Owens
Valley.
Full text of letter sent from EPA to LADWP
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY
REGION IX
75 Hawthorne Street
San Francisco, CA 94105-3901
February 27, 2002
Mr. Jerry Gewe
Assistant General Manager-Water
Los Angeles Department of Water and Power
PO Box 51111, Room 1455
Los Angeles, CA 90051
Dear Mr. Gewe:
As we discussed recently, EPA has identified the 50 cfs stand-alone pump station
as its preferred alternative for the Lower Owens River Project (LORP) Draft
Environmental Impact Statement (EIS). This is the alternative that was
originally proposed for the LORP by LADWP and the other MOU parties. This was a
difficult decision for EPA to make, as we realized that it would result in two
different preferred alternatives for the two lead agencies in the EIR/EIS, and
potentially, two different decisions in the final documents. This letter details
EPA's concerns with the 150-cfs pump station alternative.
We have continued to consider all new information as it becomes available, and
our conclusion remains: LADWP's proposal for a 150 cfs pump station is not
well-supported. The available evidence strongly suggests that LADWP prefers this
alternative in order to build future capacity to export additional water from
the Owens Valley, presumably from expanded ground water pumping. Accordingly,
the EIR/EIS must disclose these growth-inducing, cumulative and long-term
impacts. In its current form, the draft EIR/EIS has not begun to address these
impacts.
The LORP was originally conceived as mitigation for previous impacts related to
groundwater pumping dating as far back as 1972, and the project was originally
seen as a "win-win" when it was conceived (i.e., rewatering the Lower Owens
River and wetlands areas, and allowing for up to 50 cfs to be pumped back to the
aqueduct). The larger pump station, which was first proposed in February 2000,
does not appear to be justified even under LADWP's own arguments, as summarized
below.
Results of LADWP's Proposal
LADWP's change in the pump station proposal delayed the development of the EIR/EIS
by over a year, while the other MOU parties responded to and negotiated with
LADWP. As a non-signatory to the MOU, EPA was not involved in that process.
However, we observed the process, and have actively sought solutions to the
impasse, because we believe this project, .as originally proposed, can provide
environmental and water-quality benefits to the Owens Valley. EPA has been
contacted by Indian Tribes in the area, for whom we have a trust responsibility,
as well as by other MOU parties, and we have heard widespread arguments against
the larger proposal. While some of the parties who have contacted us adamantly
oppose any suggestion that could potentially lead to a larger pump station in
the future, some offered compromises, if LADWP could provide assurances that the
pump station operations would be consistent with the LORD plan, and no
additional groundwater pumping or other water exports would result. LADWP has
been unwilling to provide any assurances that additional groundwater pumping to
the pump station will not occur, or that the pump station will only be operated
as originally conceived under the LORP. In fact, LADWP recently initiated
studies to investigate the potential for additional groundwater extraction in
the basin. LADWP staff have argued that LADWP wants to build the larger facility
now because there simply is no chance that greater capacity would ever be
approved in the future.
Summary of Analysis
Under NEPA, EPA must identify which alternative is environmentally preferable,
and we must explain the basis on which a final decision is made. The smaller
pump station alternative is clearly environmentally preferable. The discussion
of alternatives can include economic considerations, so EPA requested to review
LADWP's economic feasibility analysis in order to better understand LADWP's
perspective on the larger pump station proposal. LADWP evidently had conducted
its feasibility analysis under a different set of project assumptions: the
entire seasonal habitat flow would reach the pump station, which would require
supplementation over the length of the river, due to water losses. Since that
time, LADWP has re-defined the seasonal habitat flow, so that losses would not
be supplemented and the entire flow would not be provided along the entire
river. This would affect the economic analysis. LADWP assured EPA that LADWP
would be reviewing and updating its analysis, because LADWP was not interested
in promoting a project that was not economically feasible.
We shared with you a table that we had developed from the EIR/EIS analysis,
which showed that the 150-cfs pump station capacity would not be fully utilized
at any time under standard LORP operations, assuming a water loss rate of 1 cfs/mi
from the LA Aqueduct Intake to the pump station. This appears to be a reasonable
and conservative estimate of loss from evaporation, transpiration and ground
water infiltration, particularly if one considers that the project should result
in additional growth of riparian vegetation. However, even if one considers the
smallest possible loss rate of 0.3 cfs/mi (based on the lowest loss rate that
was observed during the 1993 flow study), the capacity of the pump station would
be utilized, at best, one day every other year, or 0.5 days per year on average.
(Even the originally-proposed 50-cfs capacity pump station would be fully
utilized only 2.5 days per year, on average, or 3.5 days per year using the
lower loss rate.) Thus, the excess, underutilized capacity would provide strong
incentive for LADWP to pump additional water from the Owens Valley.
EPA remains interested in reviewing your economic analysis when it becomes
available. Meanwhile, we developed our own simplified analysis, in an effort to
understand the arguments for and against the larger pump station for the
purposes of the EIR/EIS. Our conclusions follow.
Enclosed, you will find an update of the table that we originally provided you,
which shows the amount of water that could be pumped under the two main project
options from the Lower Owens River. In theory, this water could be valued at a
price up to the replacement cost of water purchased from Metropolitan Water
District (MWD). Our conclusion is that, if water losses are minimal along the
62-mile river reach, the larger pump station may net LADWP about 180 AF per
year, on average, over the 50 cfs option. This would be worth only about $58,000
per year, which is slightly less than a 2% o annual return on the additional
investment, assuming a relatively high replacement value ($323 per AF). This
does not include the additional costs of maintenance, or of litigation that
LADWP will likely face if it decides to build the larger pump station.
Even using a smaller loss rate, which we are not confident that the evidence
will support, the larger project will net, at most, 435 AF per year, on average,
or up to $141,000 per year. Thus, using assumptions that are extremely favorable
to the larger project, LADWP may realize, at best, less than a 5% annual return
on the additional investment, but only if additional maintenance, litigation or
related costs are not factored in.
Our analysis uses the current U.S. Bureau of Reclamation (USBR) cost estimates
for constructing the 50-cfs and 150-cfs pump stations, which show that a
stand-alone 50 cfs pump station (the original proposal) will cost approximately
$5 million. The additional cost of the 150 cfs pump station is estimated at $3
million, for a total of nearly $8 million. (USBR is currently revising these
estimates, which will include additional costs for the expanded options that
were not included in the original estimate.) Using the proportions of full
service and local project water versus stored water that LADWP has purchased
from MWD over the last 10 years (70% and 30%, respectively, calculated from
quantities available on the MWD website), we assigned an overall value of $323
per AF to the pumped water. Using the full-service water value of $349 per AF is
not realistic, as water purchased from MWD has never been comprised completely
of this higher-value water during the period of record available from MWD.
Assuming a 5% rate for the cost of financing the project (municipal bonds,
presumably) and throwing in a 1% annual increase in the cost of replacement
water from MWD, it could still take up to 70 years to recover just the
construction cost difference between the larger pump station and the original
proposal, assuming that very little water is lost in the 62-mile reach between
the Intake and the pump station.
Conclusions
LADWP's proposal for the larger pump station does not appear to be economically
or environmentally justified. Pushing the proposal forward will continue LADWP's
litigious relationship with Inyo County and the other MOU parties, which may
result in significant and unrecoverable financial and public-relations burdens
for the City of Los Angeles.
EPA, as a major contributor to the LORP (with over $6 million currently
earmarked for the project, including over $1.5 million for the City of Los
Angeles), must meet fiscal and legal requirements in funding the project. Among
them is the requirement to produce an adequate EIS, which fully discloses all
the impacts of the project to the public and decision-makers, and to consider
public comments on the proposal. EPA is also required to document our decision,
which becomes part of the public record. Given the public scrutiny that this
project is likely to undergo, we are concerned about LADWP's continued
preference for the larger pump station, and we will require that the draft EIR/EIS
adequately disclose all impacts, including growth-inducing, cumulative, and
long-term impacts.
The original 50-cfs pump station alternative is the better proposal to meet the
intent of the LORP ' for the purposes of EPA's funding. Should LADWP decide to
go ahead with the 150-cfs alternative, LADWP would be responsible for all costs
above those that would be incurred by EPA's selected project. Even under that
scenario, full disclosure of impacts associated with the larger pump station
alternative will be required.
Thank you for your consideration of this matter. If you would like further
discussion, please call me at 415-972-3456.
Sincerely yours,
Janet Parrish
Monitoring and Assessment Office (WTR-2)
|